IKPT Successfully Completes CAP ECCx Project Early
PT. Chandra Asri Petrochemical Tbk (as the Owner) and Consortium of Toyo Engineering Corporation and PT. Inti Karya Persada Tehnik was signed contract for Detailed Engineering Procurement and Construction for Ethylene Plant Capacity Expansion from 600 KTA to 820 KTA on September 13, 2013. The plant location in Cilegon, Banten, West Java – Indonesia.
That the Mechanical Completion Declaration for CAP ECCx Project was received from PT Chandra Asri Petrochemical on December 9, 2015, which is 3 days ahead from contractual require dated on December 12, 2015.