EPC Geothermal Fluids Production and Reinjection Facility of Ulubelu Unit 1 & 2 Project
Client : PT. Pertamina Geothermal Energy
Capacity : 2 x 55 MW
Period : May 2011 – May 2013
Location : Muara Dua Village, Ulubelu District, Lampung, Sumatera
IKPT was completed build a Geothermal Power Plant in Ulubelu, Lampung – Southern Sumatra. This Project EPCC (Engineering, Procurement, Construction, & Commissioning) for Geothermal Power Plant of SAGS (Steam Field Above ground Gathering System) Unit I & II with capacity is 2 x 55 MW Electric Power.
IKPT scope of work is to build Two Phase & Steam Pipelines app. 12 Km, spread out from several wells, and also separation & purification of steam.
To supply Interface Pressure 8.4 bar, Steam Flow 8 Ton/H/MW with 99% dry steam for Power plant 2x55MW.
This project has been performed successfully and “kept safe man-hours” until completion with “zero accident”.