Ceremony of Compression-2 Project at Site, Southern Sumatra
Compression Phase-2 Project started on July 27, 2015. It is a small project owned by International Oil & Gas company, located in Southern Sumatra.
IKPT Scope of Work in this project are :
- Modification well area
- Modification gas turbine compressor
- Modification compressor after cooler
- Modification of support facilities
The project duration is 13 months from July 27, 2015 to August 26 2016. The project successfully completed by achieving Mechanical Completion on July 18, 2016. This means the schedule is ahead for 40 (forty) days with Zero Total Recordable Injury Rate (TRIR).
On Wednesday, August 17, 2016 in site, South Sumatra the “Celebration for Closing Project” was conducted and opened by IKPT Project Manager, then Client Lead Engineer and IKPT Project Director.
The event was attended are Client Team, IKPT Team and the representative of subcontractors.
Symbolizing of the Celebration for Closing Project was continued by cutting off a yellow rice (call Nasi Tumpeng) as the ultimate program performed by IKPT Project Director, and a piece by piece delivered to the following :
- Client Lead Engineer
- Client Operation Superintendent
The last celebration was having lunch together with all project team.