LNG Train H Project
Client : PT. Badak NGL Co.
Capacity : 2.95 Million Tons
Period : Maret 1997 – November 1999
Location : Bontang, Kalimantan Timur
EPC Work for Train-H LNG Processing plant including Plant-1 CO2 Removal Unit (aMDEA solvent – BASF licensor), Plant-2 Dehydration & Mercury Removal Unit, Plant-3 Fractionation Unit, Plant-4 Refrigeration Unit and Plant-5 Liquefaction Unit (APCI licensor).
Utilities and Offsite includes Pipeline 42″-57km, Condensate Storage Tank 12,000m3, FG KOD, LNG Storage Tank 127,000m3, Boiler 3x379t/h capacity, STG 12.5MW, GTG 13.5MW, Seawater Pump 3x3MW, Hypochlorite Unit 50kg/h, Nitrogen generation package 200Nm3/h, ESD system, F&G system and others.