IKPT's
Management has decide to
participate in this project and
has signed the MOU with Chiyoda
Corp. to involve IKPT's Engineer
during the course of Engineering
in Chiyoda Yokohama office. |
 |
It is also
possible that IKPT's Engineer
will be assigned at Plant site -
Qatar. |
 |
It is
expected 25 IKPT's Engineer will
be assigned to Yokohama starting
January 2005 for 1 year
assignment. |
 |
The
objective of IKPT participate on
this project is in order to
entry International Market which
based on the IKPT's experience
and capability and collaborate
will Chiyoda. |
 |
IKPT has
dispatched 15 - 20 engineers to
Chiyoda office at Yokohama and
Chiyoda still requested more
IKPT's engineers to assign in
Yokohama. |
 |
IKPT has
opened their Branch Office in
Yokohama (near Chiyoda Office)
with the purpose to facilitate
IKPT Engineers for their
assignment in Chiyoda Office
Yokohama. |
|
Owner |
: |
Qatar Gas
II
(70% Qatar Petroleum, 30% Exxon
Mobil). |
|
Owner
Objective |
: |
To build
the expansion LNG Plant with
capacity 2 LNG Train x 7,8 MMTPA
(Total 15,6 MMTPA)
Qatar Petroleum wish to be the
bigger LNG Producer in the
world. |
|
Project
Location |
: |
Ras Laffan,
Qatar |
|
Project
Schedule |
: |
January
2005 - End 2007 (36 months)
1 delivery of LNG January 2008 |
|
Project
Type |
: |
Expansion |
|
Scope of
work |
: |
Engineering
Services. |
|
Technology |
: |
APCI
License. |
|
Execution /
EPC Contractor |
: |
Joint
Venture of Technips and Chiyoda
Corporation. |
 |
Chiyoda will develope the
process area LNG Train |
 |
Technip
will develop the offsite area |
 |
Technip
Paris office will conduct the
engineering off sites and
associate utilities |
 |
Chiyoda Yokohama office
will be center of Project
Direction and engineering of
LNG Trains |
 |
Ras Laffan office will be
center of Construction
utilities |