Project Description
Detail Engineering, Procurement and Construction for the Betara Gas Plant, Gas Recovery Facilities, Infrastructure
Betara Gas Plant: Amine Unit and Incineration, Gas Compression, Gas Re-injection, Membrane and Pre-Treatment, NGL Recovery, Power Generation and Distribution, Process Building and Shelter, Product Storage, Sales and Gas Metering and Tie-in to PGN line, Utilities, Water Disposal, Gas Recovery System
Infrastructure: Administration, Maintenance and Safety Facilities, Construction Camp, Permanent Camp, Road Scada & Integrated Control System, Telecommunication.
Main Equipment: Boiler & HRSG, Nitrogen Generator, Flare, Water Treatment, WWT, Combustion Turbine Generator (CTG) & EDG, Fuel Gas Booster Compressor, Pumps, Heat Exchanger, Air Cooler, Pressure Vessel, Switchgear, Transformer, UPS, DCS, etc.

Profile Project
Client : Petrochina International (PCI) Jabung Ltd.
Schedule : 27 months (May'03 - Dec'05)
Value : UD $ 315 million
Plant Site : Jabung, Jambi, Sumatra
Contractor : Is the nominated s/c of Chiyoda - IKPT
Capacity : 100 MMSCFD of Sales Gas,
22,200 BPD of LPG and
27,000 BOD of Condensate
Scope of Work : EPC & Commissioning