On On 30 June
2004, an EPC contract agreement for the
Development Project Of Gas South Part of
Sumatra (Sumatera Bagian Selatan – SBS)
was signed between Pertamina and IKPT.
This Project represented an effort to
develop Gas potency in SBS to fulfill
the requirement of gas for West Java of
250 million cubic foot/feet per day,
starting mid 2006. The development
Project Gas of Sumbagsel consisted of
three packages and IKPT was awarded
package 2 and 3.
Package 2
Project of Development of Transmission
Gas and Compression facilities at West
Musi with the project value of US$
135.923.000, execution is scheduled for
24 months. The contractor is PT. Inti
Karya Persada Tehnik.
Package 3
Project Development of gathering
facility for Gas at Merbau and Delivery
facility for Gas of Pagardewa DOH SBS.
Project valued at US$ 68,819,000 Dollar
and execution schedule is 24 months. The
contractor is PT. Inti Karya Persada
Tehnik.